CWI Exam · Part C · Code Application

CWI Practice Questions — D1.1 Code Application

Ujian CWI Bagian C menguji kemampuan Anda untuk menavigasi dan menerapkan kode pengelasan di bawah tekanan waktu. Pertanyaan-pertanyaan latihan ini berfokus pada aplikasi kode D1.1:2025 — pencarian Preheat, penentuan ukuran las fillet, aturan prakualifikasi, dan variabel esensial. Setiap jawaban mengutip pasal atau referensi tabel tertentu.

Cara menggunakan pertanyaan-pertanyaan ini: Baca skenario, coba jawab, lalu lihat solusinya. Setiap jawaban mengutip pasal atau tabel D1.1 tertentu. Gunakan Flux di atas untuk mengajukan pertanyaan lanjutan tentang topik apa pun yang Anda anggap menantang.

Preheat — Tabel 5.11

Q1: A572 Gr.50 plate, 1 inch thick, welded with FCAW using E71T-1. What is the Minimum preheat?
Answer: 50°F (10°C). A572 Gr.50 is Group II in Table 5.11. E71T-1 is a Hidrogen Rendah Elektroda, placing it in Kategori B. For Group II, Category B, Ketebalan over 3/4 through 1-1/2 inch: minimum preheat is 50°F.
Q2: Same steel and thickness, but the welder switches to E71T-11 (self-shielded FCAW). Does the preheat change?
Answer: Yes — dramatically. E71T-11 is a Bukan Hidrogen Rendah electrode, moving the WPS to Category A in Table 5.11. For Group II, Category A, 1 inch thickness: minimum preheat jumps to 150°F (65°C). This is a common exam trap — the only change is the electrode classification, but the preheat triples.

Ukuran Las Fillet — Tabel 7.7

Q3: You are Pengelasan a 1/2-inch plate to a 3/4-inch plate using E7018 (SMAW). What is the minimum Ukuran Las Fillet per Tabel 7.7?
Answer: 3/16 inch. Per Table 7.7 Footnote A, when using a low-hydrogen process (E7018), T equals the thinner part joined (1/2 inch). For T over 1/4 through 1/2 inch, minimum fillet Ukuran is 3/16 inch. If the welder used a non-low-hydrogen process without preheat, T would equal the thicker part (3/4 inch), requiring 1/4 inch minimum.
Q4: The Engineer specifies a 3/16-inch Las Fillet on 1-1/4-inch thick A36 plate using E6013 without preheat. Is this acceptable?
Answer: No. E6013 is a non-low-hydrogen electrode, so per Table 7.7 Footnote A, T equals the thicker part (1-1/4 inch). For T over 3/4 inch, minimum fillet size is 5/16 inch. The 3/16-inch Las is undersized. Additionally, Table 5.11 requires 150°F preheat for Group I, Category A at this thickness (over 3/4 thru 1-1/2 inch) — but the scenario says no preheat was applied, which is also non-compliant.

WPS Prakualifikasi — Pasal 5

Q5: A fabricator wants to prequalify a WPS using GMAW short-circuit transfer on 1/2-inch A36 plate. Can this be prequalified?
Answer: No. D1.1:2025 Clause 5 does not include GMAW with short-circuiting transfer (GMAW-S) from prequalification. The fabricator must qualify the procedure by Pengujian under Clause 6. Spray transfer, globular transfer, and pulsed-spray GMAW are prequalified when all other Clause 5 conditions are met.
Q6: Can a prequalified WPS use a single-V groove joint with a root opening less than the D1.1 minimum?
Answer: No. Prequalified joint dimensions must conform to the tolerances shown in Figure 5.1 (CJP groove welds), Figure 5.2 (PJP groove welds), or Figure 5.3 (fillet welds). Any deviation from these prequalified joint dimensions — including root opening, groove angle, root face, or land — requires WPS qualification under Clause 6.

Variabel Esensial — Tabel 5.5

Q7: A fabricator changes from E7018 to E71T-1 on a prequalified WPS. Is a new WPS required?
Answer: Yes. This is a change in Proses Pengelasan (SMAW to FCAW), which is an essential variable per Table 5.5. A new prequalified WPS must be written for the FCAW process. However, since both E7018 and E71T-1 are low-hydrogen electrodes (Category B in Table 5.11), the preheat Persyaratan remain unchanged.
Q8: On a prequalified WPS, the welder changes position from 1G (flat) to 3G (vertical). Does this require a new WPS?
Answer: Yes. Position is an essential variable in Table 5.5. However, because this is a prequalified WPS, no qualification testing is required — the fabricator simply writes a new prequalified WPS specifying the 3G position with appropriate parameters for vertical welding.

Pertanyaan Silang ASME IX

Q9: A welder is qualified under ASME IX for SMAW on P-Number 1 materials. Can they weld structural steel under D1.1 with no additional testing?
Answer: No. ASME IX and D1.1 maintain completely independent qualification systems. An ASME IX WPQ does not satisfy D1.1 Clause 6 Part D welder qualification requirements. The welder must qualify separately under D1.1. In practice, many welders hold both qualifications.
Q10: What is the key difference between ASME IX supplementary essential variables and D1.1 essential variables?
Answer: ASME IX has a three-tier system: essential, supplementary essential, and nonessential variables per the QW-250 series. Supplementary essential variables become essential only when impact testing is required by the construction code. D1.1 has only two tiers: essential (Table 5.5 for prequalified, Table 6.6 for qualified) and nonessential. There is no supplementary essential concept in D1.1.

"Pada ujian CWI Bagian C, manajemen waktu adalah segalanya. Anda memiliki 2 jam untuk 60 pertanyaan buku kode. Itu berarti 2 menit per pertanyaan. Jika Anda tidak dapat menemukan tabel atau pasal dalam 30 detik, tandai dan lanjutkan. Beri tab pada buku kode Anda dengan catatan tempel untuk Table 5.11, Table 7.7, Table 5.5, Clause 5, dan Clause 6 — ini adalah bagian yang paling sering diuji."

— Field observation, CWI exam preparation practice

Tips Ujian CWI: Ujian Bagian C memungkinkan Anda membawa buku kode yang sudah diberi tab dan disorot (tanpa catatan tulisan tangan). Fokus persiapan Anda pada pencarian tabel yang cepat daripada menghafal. Mengetahui DI MANA menemukan jawaban lebih berharga daripada menghafal jawaban itu sendiri.

Panduan Standar Terkait

Pertanyaan yang Sering Diajukan

Berdasarkan D1.1:2025 Tabel 5.11, A572 Gr.50 termasuk dalam Grup II. Untuk FCAW (Proses Pengelasan Hidrogen Rendah, Kategori B), preheat minimum untuk Ketebalan lebih dari 3/4 hingga 1-1/2 inci adalah 50 derajat F (10 derajat C). Jika menggunakan Proses Pengelasan Bukan Hidrogen Rendah seperti FCAW-S dengan E71T-11, baja berpindah ke Kategori A, membutuhkan 150 derajat F (65 derajat C) untuk Rentang Ketebalan yang sama.

Berdasarkan D1.1:2025 Tabel 7.7, Ukuran Las Fillet minimum ditentukan oleh bagian yang lebih tebal yang disambung (T) saat menggunakan Proses Pengelasan Bukan Hidrogen Rendah tanpa Preheat, atau oleh bagian yang lebih tipis yang disambung saat menggunakan Proses Pengelasan Hidrogen Rendah. Untuk Proses Pengelasan Hidrogen Rendah (E7018, E71T-1, ER70S-6): T sama dengan bagian yang lebih tipis (1/2 inci), membutuhkan Minimum 3/16 inci. Untuk Proses Pengelasan Bukan Hidrogen Rendah tanpa Preheat: T sama dengan bagian yang lebih tebal (3/4 inci), membutuhkan Minimum 1/4 inci.

Tidak. D1.1:2025 tidak menyertakan GMAW-S (transfer sirkuit pendek) sebagai Proses Pengelasan prakualifikasi. GMAW sirkuit pendek memiliki risiko Incomplete Fusion yang lebih tinggi, terutama pada material yang lebih tebal, dan membutuhkan kualifikasi WPS melalui Pengujian Kualifikasi di bawah Clause 6. Mode transfer GMAW lainnya (spray, globular, pulsed-spray) adalah prakualifikasi ketika semua persyaratan Clause 5 lainnya terpenuhi.

Perubahan dari E7018 (SMAW, A5.1) ke E71T-1 (FCAW-G, A5.20) adalah perubahan dalam Proses Pengelasan (SMAW ke FCAW), yang merupakan Variabel Esensial di bawah D1.1 Tabel 5.5. Ini membutuhkan WPS baru. Namun, kedua elektroda adalah Hidrogen Rendah dan termasuk dalam Tabel 5.11 Kategori B, sehingga persyaratan Preheat akan tetap sama. WPS FCAW yang baru masih dapat Prakualifikasi di bawah Clause 5 jika semua kondisi prakualifikasi lainnya terpenuhi, termasuk Joint Design yang sesuai dengan Gambar 5.1 hingga 5.3.

Untuk WPS Prakualifikasi di bawah D1.1 Clause 5, posisi terdaftar sebagai Variabel Esensial dalam Tabel 5.5. Mengubah dari 1G (datar) ke 3G (vertikal) membutuhkan WPS baru atau yang direvisi. Namun, ini tidak memerlukan Pengujian Kualifikasi ulang karena WPS adalah Prakualifikasi. Fabricator cukup menulis WPS Prakualifikasi baru yang menentukan posisi 3G, dengan parameter yang sesuai untuk Pengelasan vertikal (biasanya Arus lebih rendah, teknik anyaman). Untuk WPS yang terkualifikasi di bawah Clause 6, Welder juga harus memiliki kualifikasi kinerja dalam posisi 3G.