AWS D1.1:2025 · Table 5.11 · Category A

A106 Gr.B Preheat for SMAW (non-low-hydrogen) — up to 3/4"

Minimum preheat and interpass temperature for A106 Gr.B welded with SMAW (non-low-hydrogen) at up to 3/4" thickness, per AWS D1.1:2025 Table 5.11.

Built on AWS D1.1:2025 Table 5.11 — every value traced to the clause.

Minimum Preheat & Interpass Temperature
32°F / 0°C
Category A Non-low-hydrogen SMAW process
AWS D1.1:2025 Table 5.11, §5.7
When base metal temperature is below 32°F [0°C], preheat to minimum 70°F [20°C] and maintain during welding (Table 5.11 footnote a).
Reference tool. Verify against project-applicable edition and Engineer-approved WPS.

Have a preheat question? Ask Flux

SMAW (Non-Low-Hydrogen)

Non-low-hydrogen SMAW (E6010/E6011) uses cellulosic electrodes with higher hydrogen potential, assigned to Category A in Table 5.11.

On pipe joints, non-low-hydrogen SMAW root passes with E6010 use the keyhole technique to ensure complete penetration. Pipe rotation (roll welding) is preferred when practical; fixed-position welding requires 5G or 6G qualified procedures. The cellulosic coating generates significant spatter, so adjacent base metal should be protected with anti-spatter compound.

SMAW Tips for Pipe and Tube Steels

For A106 Grade B seamless pipe (35 ksi yield, high-temperature service), E6010 provides the root pass on structural nozzle connection welds where access constraints prevent machine welding. Note that ASME B31.1 power piping and B31.3 process piping codes generally require full qualification of any SMAW procedure under ASME Section IX, which imposes its own electrode and preheat requirements.

Typical values for reference — always verify against your approved WPS and electrode manufacturer data.

Filler Metal for SMAW

Electrode: E6010 (DC+ only) or E6011 (AC/DC) per AWS A5.1. Cellulosic coating — NOT low-hydrogen. Diameter: 1/8" (root passes, all-position), 5/32" (fill passes). No oven storage required. These electrodes intentionally produce higher hydrogen for deeper penetration — the tradeoff is higher required preheat per Table 5.11 Category A.

Typical values for reference — always verify against your approved WPS and electrode manufacturer data.

A106 Gr.B

ASTM A106 Grade B covers seamless carbon steel pipe for high-temperature service up to about 750°F, with 35 ksi minimum yield and 60 ksi minimum tensile strength. Produced in sizes from 1/4" through 30" NPS, it is the standard pipe material for power plants, refineries, and process piping where elevated temperature and pressure coexist. Chemistry limits (0.30% max carbon, 0.29-1.06% manganese) give it a weldability profile that matches common structural grades with Category A and B preheat requirements. A106 is exclusively seamless, which eliminates the ERW seam concern present in A53. Grade C (40 ksi yield) exists but Grade B handles the vast majority of process piping service.

Why This Preheat for A106 Gr.B with SMAW

Seamless pipe rated for high-temperature service up to 750°F. At this thickness, SMAW with non-low-hydrogen electrodes places the joint in Category A of Table 5.11. The minimum preheat of 32°F compensates for the higher diffusible hydrogen from cellulosic electrode coatings. The thicker the material, the longer hydrogen takes to escape the heat-affected zone, which is why preheat rises with thickness even for this common grade.

Typical Applications for A106 Gr.B

Used in boiler steam headers, refinery piping racks, process plant branch connections, heat exchanger nozzle welds, power plant main steam lines, petrochemical reactor feed piping, and high-temperature manifolds. A106 Gr.B butt welds in process piping require joint preparation to B31.1 (power piping) or B31.3 (process piping) depending on service classification. Socket welds on small-bore A106 drain lines and instrument take-offs are common in utility stations, typically 1/2" to 2" NPS. Typical wall thicknesses range from Schedule 40 (0.237" wall on 2" NPS) to Schedule 160 (0.500" wall on 4" NPS) in critical high-energy service. Weld procedure qualification often includes side bend tests and tensile tests specific to the pipe diameter and wall thickness being joined. Field welds at pipe-to-flange connections and valve set-on joints require portable preheating equipment when wall thickness exceeds 1/2".

Why Preheat Matters at up to 3/4"

Thin material sheds heat quickly, allowing hydrogen to escape the HAZ readily — lowest preheat tier in Table 5.11.

Why 32°F for A106 Gr.B?

A minimum preheat of 32°F (0°C) means no active preheating is needed above freezing conditions. Table 5.11 Category A at this thickness assigns the ambient minimum because A106 Gr.B with non-low-hydrogen SMAW has sufficient ductility and low enough carbon equivalent that hydrogen cracking risk is minimal at this section thickness. Per footnote (a), if working below 32°F, preheat the joint to at least 70°F (20°C) and maintain during welding.

Other Steels with SMAW (non-low-hydrogen) at up to 3/4"

SteelCategoryPreheat
A36A32°F (0°C)
A53 Gr.BA32°F (0°C)

Try Different Combinations

Use the interactive preheat calculator to look up any steel, process, and thickness combination from D1.1:2025 Table 5.11.

What is the minimum preheat for A106 Gr.B with SMAW at up to 3/4"?
When welding A106 Gr.B at up to 3/4" using SMAW, the minimum preheat temperature is 32°F (0°C) per AWS D1.1:2025 Table 5.11, Category A. SMAW places this combination in Category A. This is also the minimum interpass temperature — the joint must not cool below 32°F between passes.
What Table 5.11 category applies to A106 Gr.B with SMAW?
When using SMAW on A106 Gr.B, the combination falls under Category A in AWS D1.1:2025 Table 5.11. Non-low-hydrogen SMAW process. At up to 3/4" thickness, Category A with SMAW requires a minimum preheat of 32°F (0°C).
Does A106 Gr.B need preheat at up to 3/4"?
When welding with SMAW at up to 3/4" thickness, the minimum preheat is 32°F (0°C) — effectively ambient temperature above freezing. SMAW with this steel requires no active preheating unless the base metal is below 32°F. Per Table 5.11 footnote (a), if working below freezing, preheat to at least 70°F (20°C) and maintain during welding.
Is preheat needed for plate under 3/4 inch?
For most structural steels at this thickness, the Table 5.11 minimum is 32°F (0°C) — ambient temperature above freezing. The thin cross-section allows hydrogen to diffuse out readily. Per footnote (a), if working below freezing, preheat to at least 70°F (20°C) and maintain during welding.

D1.1:2025 reference data. Not affiliated with AWS.